Project Schedule
| RFQ for Construction Manager at Risk |
July 2012 |
| Council Approval of Construction Contract |
September 11, 2012 |
| Dry Utility Relocations | Sept. 2012 – Jan. 2013 |
| Pinnacle Peak Intersection Improvements | October 2012 |
| Water & Sewer Relocations |
Oct. – Nov. 2012 |
| Bridge |
Dec. 2012 – July 2012 |
| Public Art | Aug. 2013 |
| Pavement Overlay* | Sept. 2013 |
| Construction Complete | October 2013 |
*Additional details will be provided as they become available.
For additional information please see the Construction Sequence Map.