The roundabout originally planned at the intersection of Scottsdale and Dynamite roads is being reviewed by staff – a traditional signalized intersection is also being considered. Staff and project team members are further evaluating these alternative intersection designs and are identifying potential impacts.
Crews are currently working on the east side of Scottsdale Road, off the roadway, to conduct native plant salvage. This involves boxing and relocating trees to a contractor nursery where they can be maintained during construction, to be replanted in the project area as the project nears completion.
Scheduled to begin in early March, crews will work to complete installation of storm drain pipe in the northbound lane (east side) of Scottsdale Road, from Jomax Road north toward Redbird Road. Scottsdale Road traffic will be reduced to one lane in each direction, shifted to the west side of Scottsdale Road. Left turns may be restricted during this storm drain work, which is expected to take about 2-3 weeks to complete.
Currently scheduled to take place in mid to late March, crews will work at the Dixileta Drive intersection to install a temporary traffic signal to be able to relocate the existing traffic signal further back as part of the planned improvements at that intersection.
Utility work continues by various utilities to relocate their facilities out of the way of the planned improvements. This utility work is expected to be complete in late March.
During construction, lane reductions and turn restrictions may be in place, as needed, to shift traffic away from the work zone. Please obey traffic signage as it is placed for the safety of residents, travelers and construction crews. Traffic control remains in place 24/7 to protect the work zone, and speed limits are reduced near the work zone. Work primarily takes place during daytime hours, weekdays; however, it may be necessary, at times, to conduct work during night hours or weekend days.